The Arbor Homes built Magnolia model to be built in Whispering Falls on the 22 acre pond/lake
 
To see all photos do not click a link below and just scroll down. You can click most recent for latest photos.
 
breaking ground      footers      slab poured      framing delivered      framing started      more framing      framing finished
 
windows      roofing      fireplace      drywall      brick and siding      driveway and sidewalk      cabinets and trim
 
flooring - tile      flooring - carpet      getting close      most recent      last photo (then scroll up)     
 
_______________________________
 
May 24th, 2012

_______________________________
 

_______________________________
 
August 26th, 2012

_______________________________
 

_______________________________
 

_______________________________
 

_______________________________
 

_______________________________
 

_______________________________
 

_______________________________
 

_______________________________
 

_______________________________
 
breaking ground - January 26th, 2013

_______________________________
 

_______________________________
 
footers - February 14th, 2013

_______________________________
 

_______________________________
 

_______________________________
 
slab poured - February 23rd, 2013

_______________________________
 

_______________________________
 

_______________________________
 
framing delivered - February 28th, 2013

_______________________________
 

_______________________________
 
framing started - March 6th, 2013

_______________________________
 

_______________________________
 
framing started - March 7th, 2013

_______________________________
 

_______________________________
 

_______________________________
 
more framing - March 8th, 2013

_______________________________
 

_______________________________
 

_______________________________
 

_______________________________
 
more framing - March 9th, 2013

_______________________________
 

_______________________________
 
more framing - March 10th, 2013

_______________________________
 

_______________________________
 

_______________________________
 

_______________________________
 
more framing - March 12th, 2013

_______________________________
 

_______________________________
 

_______________________________
 

_______________________________
 

_______________________________
 
framing finished - March 13th, 2013

_______________________________
 

_______________________________
 
windows - March 14th, 2013

_______________________________
 

_______________________________
 
roofing - March 16th, 2013

_______________________________
 

_______________________________
 
fireplace - March 19th, 2013

_______________________________
 

_______________________________
 

_______________________________
 
drywall delivered - March 21st, 2013

_______________________________
 

_______________________________
 
drywall - March 25th, 2013

_______________________________
 

_______________________________
 
March 26th, 2013

_______________________________
 

_______________________________
 
brick and siding -March 27th, 2013

_______________________________
 

_______________________________
 
March 28th, 2013

_______________________________
 

_______________________________
 
driveway and sidewalk - April 6th, 2013

_______________________________
 

_______________________________
 
cabinets and trim - April 9th, 2013

_______________________________
 

_______________________________
 
cabinets and trim - April 12th, 2013

_______________________________
 

_______________________________
 

_______________________________
 
April 15th, 2013

_______________________________
 
flooring-tile - April 18th, 2013

_______________________________
 

_______________________________
 
NOTE: at this point with interior painting, cabinets, and flooring going in the house is now being
locked by the builder so getting more photos of the interior of the house from this point forward will not
happen as often as I have to plan it when I know they are there inside working. Carpet is planned for April 24th-25th.
 
_______________________________
 
flooring-carpet - April 25th, 2013

_______________________________
 

_______________________________
 

_______________________________
   
getting close - May 1st, 2013
 
Getting real close now to being completed. Yard not graded or sod down yet.
Had meeting today with construction manager and noted items needing fixed/touch up.
Looking good! Getting excited! Schedule to close on the house May 14th.
Will meet with the construction manager one more time before closing to check the house out again.
 

_______________________________
 

_______________________________
 

_______________________________
 

_______________________________
 
getting close - May 11th, 2013
 
Grading of yard done and "token" 5 mini shrubs and 2 mini trees are in. OK. Wow! LOL
I will plan on replacing those for sure with some bigger and different ones and put those there now to the back yard.
 

_______________________________
 

_______________________________
 
 

back to the top of page
 
Blue water view from the 2nd story of the house while being built. Photo taken March 19th, 2013.
 

 
** END **
 